Wednesday, April 8, 2015

#9 and #10 Update

The first 2 photos are some completed bunkers on #9. The first one is by the green and the second photo is a right side fairway bunker about 100 yards out from the green.



This photo was taken last night. All of the right side bunkers have been built and have drainage installed in them. Right now they can not go any further because of the rain that is forecasted for this afternoon and this evening. If they install the liners and the sand we could have some contamination because the sodding is not completed around the outside of the bunker.


If they can not work on #10 today I am sure that they will be working their punch list items.