Monday, October 20, 2014

Week 9 Recap

Week 9 Recap
I am sorry that I am late in getting an update written this week. We finally hit a stretch of nice weather and we have worked non-stop trying to get things done.

We had a lot of rain at the start of the week that basically shut us down for 2.5 days. By Wednesday we were able to get started working again. All of the work around #13 green has been completed. #14 tees are all seeded and the cart path work and sodding is about completed. By Tuesday we should be out of that are completely.

All of the new tees have now been graded except for #10 tee. Leibold is really busy getting tees built, the last of the drainage in and building bunkers. Architect Tim Liddy was in last Thursday and gave them some guidance on their projects.

We are busy building the wall on #12 green while it is high and dry. Hopefully we can stay away from the rain and we can get a lot done in that area.
Sorry for the short rant this week and the lack of photos. I have been so busy I have not had a lot of time to do anything but golf course items and construction.